General Introduction
History
Presidents and Academicians
Organization
Dam Safety Management Center of MWR
Waterlocks Safety Management Center of MWR
Research Center for Climate Change of MWR
Engineering Quality Inspection Center of MWR
Hydrology and Water Resources Department
Hydraulic Engineering Department
River and Harbor Engineering Department
Geotechnical Engineering Department
Materials and Structural Engineering Department
Dam Safety Management Department
Center of Eco-Environmental Research
Research Center for Rural Water Management
State Key Laboratory of Hydrology-Water Resources and Hydraulic Engineering
Key Laboratory of Port, Waterway and Sedimentation Engineering of Ministry of Transport
Key Laboratory of Water Science and Hydraulic Engineering of MWR
Key Laboratory of Failure Mechanism and Safety Control Techniques of Earth-rock Dam of MWR
R&D Center of Hydro-Power Engineering Safety and Environmental Technology of NEA
International Joint Research Center of Water Science & Engineering
Research Center on Hydrology and Water Resources Engineering of MWR
Tiexinqiao Water Experiment Center
Chuzhou Water Experiment Center
Dangtu Water Experiment Center
River and Lake Research Center at Wuxi
NHRI Experts Rush to Huangbizhuang Reservoir in Hebei Province for Dam Safety Inspection
Post Time:2016-07-27Front:[ Large Medium Small ]

Site inspection

Ground penetrating radar (GPR) detection

Local bubbling zone

Torrential rain in North China has greatly affected the local flood control safety in recent days. From July 19 to July 20, 2016, heavy rain resulted in the rapid increase of water level of the Huangbizhuang Reservoir in Hebei Province to 8.55m within 48 hours. At about 8am of July 21, there were rolling bubbles in large water area at the auxiliary dam section of 500m within the reservoir area accompanied by sound.

The Office of State Flood Control and Drought Relief Headquarters and MWR paid high attention to these phenomena. In order to find out the causes of rolling bubbles and current dam safety state and ensure the reservoir downstream people’s life safety and normal function of the reservoir, NHRI and MWR Dam Safety Management Center sent 7 experts including Prof. YUAN Hui for the site right on the afternoon of July 21 according to the arrangement of relevant government. They reached the reservoir at 4am next day after 12 hours’ drive, and threw themselves into site investigation right away.

After field inspection, observation data analysis and preliminary analysis of GPR detection, the experts put forward the opinions on engineering quality of dam section with rolling bubbles and current dam safety state, and successfully completed the tasks entrusted by the State Flood Control and Drought Relief Headquarters and MWR. Vice Minister of Water Resource, Mr. LIU Ning fully affirmed the work done by NHRI experts with a special letter of thanks.